M20- SAW CUTTING & JOINT SEALING

UEGN4094[1].JPG

SCOPE  

THE WORKS WERE CARRIED OUT ON THE M20, BETWEEN JUNCTIONS 8 AND 9 (COASTBOUND), COVERING APPROXIMATLRY 20 KILOMETERS OF CONCRETE CARRIGEWAY.

MZKT3350[1].JPG

PROCESS 

STEP 1 : PLOUGHING OUT OLD SEALANT

STEP 2: SAWING 

STEP 3: DRYING

STEP 4: GRIT BLASTING 

STEP 5 : CAULKING 

STEP 6 : SEALING

MZKT3350[1].JPG
SXGW0052[1].JPG

COLLABORATORS

FOR THIS PROJECT, WE PARTERNED WITH ROADTEACHS and PG SWEEPERS TO DELIVER WORKS ON BEHALF OF NATIONAL HIGHWAYS ENGLAND.

image.png

STATS

TOTALM SHIFTS - 20 NIGHT SHIFTS (WORKING WINDOW 10PM - 3;30 AM)
 
TOTAL METERS CUT AND SEALED - 23,304 LnM
 
AVERAGE CUT AND SEAL PER SHIFT - 1,165.2LnM

PUHG3758[1].JPG
MOVF5019[1].JPG

MORE DETAILS

CHECK OUT OUR BROCHURE FOR MORE DETAILS ON THIS PROJECT

Logo

Little Westerhill Farm,

Westerhill Road, ME174BS 

​07768 662153

© 2023. Shepherd & Sons Contracting. All Rights Reserved. Created by Gone Rogue Web Design

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram
bottom of page